the alternative, rolling outages, carries its own serious risks.
Using backup generation. If PJM reaches an Energy Emergency Alert (EEA) 3, the point at which electricity supply is critically low, it can direct its members to run backup generators. The order also lets PJM act as a last resort before an EEA 3 is declared.
Maximum Generation Alerts. PJM can notify transmission and generation owners that the system needs maximum output. Those owners can then decide whether to defer or cancel planned maintenance and other services that would take capacity